Review of the Recycler Commissioning Plan

Committee Report
Management Closeout


Dates: Jan. 23, 2004 - Feb. 10, 2004 (First Phase)

Note: No Meetings or formal presentations are planned at this time. The committee members are requested go through the proposed Commissioning Plan document (links below) and to send comments to the committee Chair and other committee members (cc:pushpa@fnal.gov).

Goal:

Review of the Recycler Commissioning Plan

Desired outcome:

Approval of the commissioning plan and recommendations on how to proceed.

Review Committee:

John Peoples (Chair)
Helen Edwards
Dave Finley
Bill Foster
John Marriner

Charge:

The Run II upgrade plan calls for integration of the Recycler into collider 
operations in two major steps.  First, by June 1, 2004, the Recycler should 
be commissioned and its performance improved to the level that it is ready 
for implementation of electron cooling.  Second, electron cooling is to be 
commissioned and made operational by June 1, 2005.  This committee is asked 
to review the commissioning plan proposed to achieve the first goal, viz., 
commissioning and preparing the Recycler for beginning the implementation 
of electron cooling. 

To help facilitate the planning of the Recycler commissioning, a set of 
performance criteria to be met, for antiproton transfers to the Recycler, 
cooling, stacking and storing in the Recycler, and extraction, were developed 
for FY04 and beyond. They were reviewed by a committee in November 2003 and 
approved. (Ref. Performance Criteria Review Web Page )
A sub-set of these performance criteria necessary to be satisfied to complete 
the first phase of commissioning has been identified.  The commissioning plan 
document outlines these criteria, the status of the Recycler and plans to meet 
the milestone by June 1, 2004.

The specific charges for this committee are as follows:

1. Review the current status of Recycler Commissioning and plans to meet the 
performance goals for readiness of the Recycler for installation of electron 
cooling. Comment on whether the goals seem achievable by June 1, 2004.  

2. Are the operational steps and methods proposed to achieve the performance 
goals for the readiness of the Recycler to begin installation of electron 
cooling appropriate?

3. Are the proposed commissioning study periods and resources adequate to 
achieve the goals of commissioning by June 1, 2004?

4. Are there any issues ignored or underestimated in the proposed plan to 
prepare the Recycler to begin installation of electron cooling?


Documents:

The Recycler Commissioning Plan (Feb. 2004)
The Recycler Status and Commissioning Plan (Sergei's talk on Feb. 17, 2004)
Pbar transfer data - Jan. 22, 2004
Pbar trasfer data (multiple dates)
Recycler/Electron Cooling Status (Presentation at the Temple review by S. Nagaitsev (Jan. 2004)
Recycler Status (John Marriner), DOE Review July 2003
Rapid Antiproton Transfers from the Accumulator (Elvin Harms), DOE Review June 2003
Antiproton Stacking in the Recycler (A. Burov), FERMILAB-CONF-03-171

Comments from Reviewers:

Outcome:


Project Personnel:

Level 2 (WBS 20.26.3) Project Manager - Paul Derwent
Recycler Commissioning - Sergei Nagaitsev
Electron Cooling - Sergei Nagaitsev


Some Performance Milestones

							Plan		Actual
1.	Vacuum performance				01/19/04	01/09/04
2.	Vacuum and machine admittance			01/27/04	01/12/04
3.	MI to RR Trans. eff. >85%, round trip		02/27/04	-
4.	Stacking performance with 100e10		03/15/04	-
5.	Equilibrium properties at 200e10		04/05/04	-
6.	Recycler rapid transfers commissioned		04/20/04	-
7.	Extraction commissioned				05/03/04	-
8.	Recycler commissioned for electron cooling	06/01/04	-

Other Ongoing Tasks on pbar stacking & cooling:

WBS Details for Recycler Stacking and Cooling Project

Planned 2004 Shutdown Activities: (8/23/04 - 11/22/04)