Tevatron Helix and Separators Scope Review
Meeting: Tuesday, August 26, 2003
8:30 - 16:30 (Presentations: 9:00 - 15:00)
Venue: Huddle
Main reason for review:
What is the best long term plan for helix operation and separator improvements as the intensity of the pbar ( and proton) bunches is increased?
[ Scope Review (WBS 1.3.4.4.5.3)Decision on creating additional space in the lattice and to build longer separators at the interaction regions.]
Charge:
- Review the present status of the beam helix scheme and possible/proposed near-term improvements and studies
- Present status
- Separator layout and operation
- Helix description at all stages of injection to store, and possible modifications with existing hardware
- Description of aperture used in sigma and mm, also transverse vs dispersion
- Dynamic aperture investigations, and comparison with aperture used
- Beam correction and differential correction schemes
- Near-term improvements and studies
- new helix up the ramp, no polarity reversal for roman pots, collimators
- higher gradient operation (for short times), 18x18 study, crossing angle at interaction points, smaller beta* ~25cm
- studies to include summary of studies so far, study plans and time needed in future
- Review potential long-term improvements - Where new separators could go, what would need to be done, what modifications to existing hardware. What are the perceived benefits, relative effort and risk. Is the schedule reasonable?
- Review and comment on possible gains from improvements.
- Comment on the technical plan for increasing the separators gradient. should this be part of the RunII Program or a separate R&D project?
- Suggest other possible approaches. Is there a consistent intergrated approach?
Upcoming Project Decisions
9/1/03 - Pursue additional and/or longer separators? Understand impact on other hardware, etc., that would need to be removed, relocated or modified.
4/28/04 - Pursue higher voltage operation and/or continue R&D
Agenda
08:30 - Executive Session
09:00 - 15:00 Presentations
Vladimir Shiltsev - Intro/Charge (20')
Ron Moore - Project Overview (20')
Tanaji Sen - Dynamic Aperture (45')
Yuri Alexahin - Optimizing Helices with Current Separator Configuration (45')
John Johnstone - Future Helix Upgrades (45')
Bruce Hanna - Separator Operation and Impact of Additional and/or Longer Separators
Rodger Bossert - Fabrication of Separators and Polarity Switches (20')
Gennady Romanov - R&D Correction Schemes, Feed-down Circut Operation, Modifying Lattice at A0 Straight Section (30')
Ron Moore - Summary (15')
15:00 - 16:30 Executive Session
There will be a lunch break and coffee/stretch breaks.
Presentation time limits INCLUDE 5-10 minutes for questions/discussions.
Reviewers
Helen Edwards (chair)
Gerry Annala
Dave Finley
Mike Syphers
Charlie Sinclair
Dave Rubin
Gerry Dugan
Documents:
Committee Report:
Outcome:
Project Personnel
Ron Moore - Project Manager
John Johnstone - Future Helix Upgrades
Yuri Alexahin - Optimize Separation with preasent separators
Bruce Hanna - Tevatron Polarity switches for separators, coating of separators
Gennady Romanov (TD) - R&D for coating of separator electrodes
Rodger Bossert (TD) - Fabrication of polarity switches and separators
Jim Walton (Tev Dept) - Separator and power supply expert;
conditioning/commissioning separators
Contact: Pushpa Bhat